Bond Progress Report - 6/28/2012

July 10, 2012

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Work continues on the first floor in all rooms except 4 at the back of the building. These 4 will be the last phase and should start in late August. Classrooms in the front of the building are nearing completion. I anticipate these will be complete about July 23rd. Work continues on the office area and science wings and we will be pushing to get them completed by August 15th.

Goliad Project:

Work continues in the south wing. We are putting everything back to gether on the final wing at Goliad. Painting is in progress as wel as wainscot tile in the hallways. Ceiling grid is going in and plumbing and electrical are in the final stages of completion. We should be through here in early August.

San Jacinto Project:

We have moved back into all parts of the main building. The 50’s wings are progressing with painting about finished. Flooring will start as soon as we get the air going. The kitchen tile is complete and they should start the rest of the cafeteria soon. This should all be complete in August.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations: The Student Service Center is complete and operational.

Banneker 1: Complete

Banneker 2: The behavior management class is in and occupancy should be awarded next week.

Schweitzer: We moved into Schweitzer and should get the final occupancy certificate next week.

Cafeteria: Area has been demolished and masonry walls have started for the restrooms and snack bar. Overhead electrical will have to be reworked due to age and lack of conduits. We could not see any of it until the plaster was removed and it fell out of the ceiling structure.

Courtyard: The interior courtyard has been demolished and the new landscape, masonry, and lighting will begin in the next week. We are adding pavers and low-maintenance, low-water plantings. This should be complete in early August. The parking lot behind Tucker has also been demolished to prepare for new walks.

Michelangelo: We are completing the east end of this building for choir. It should be ready in early August.

Crockett Project:

Work on the north wing is progressing as well as the cafeteria and site work. A quick drive by the site will reveal a lot of demolition for new parking and drives on Johnson Street.

Glenmore Project:

We are in the final stages of the new addition and almost complete with all demolition in the 14 classroom addition on the south side of campus and the administration building on the north side. All classrooms will be complete in early August but the office area will not be complete until October.

Bradford Project:

Steel erection is underway and will continue for the next month.

Reagan Project:

We have moved into the upstairs at Reagan and vacated the downstairs of the main building. Demolition is already underway on the downstairs.

Lake View Project:

Our estimates on Lake View came in close enough to budget so we have started the design phase of the project and should have a guaranteed maximum price from the contractor in September with construction to start in October.