Bond Progress Report - 9/7/2012

September 14, 2012

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

The main part of the building is complete except for the four rooms on the north hallway. They are projected to complete these rooms around November 1st. At that time we should be in the process of moving the portables and preparing for the track installation. They are putting the finishing touches on the big gym and should complete that by September 17th. Work on the fieldhouse continues and should be ready for occupancy near the first of October.

Goliad Project:

This project is 99% complete. We still need to finish the fencing and some landscape work along with some punch list items.

San Jacinto Project:

We made it for the first day of school. We were there on Sunday evening before school started putting together the cafeteria tables but it was useable on Day 1. We continue to work on the 1950’s buildings and a lot of punch list and exterior items. We should be finished with this project by the first of November.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations: The Student Service Center is complete and operational.

Banneker 1: - Complete.

Banneker 2: Complete.

Schweitzer: - Complete.

Cafeteria: The cafeteria is complete.

Courtyard: Our courtyard renovation is complete.

Michelangelo: Renovations are 99% complete. They are finishing the restrooms this weekend and it should be ready except for punch list items.

Holmes: Demolition of Holmes is almost complete and metal stud walls are going back up. The concrete is poured in the extended classrooms on each corner and plumbing is going into the renovated restrooms. This project is scheduled for completion around Christmas.

Crockett Project:

The older wings on the north and south are starting to come together. The north wing is about 90% complete and the south about 80%. Work on the cafeteria was complete when school started.

Glenmore Project:

The new addition is complete and the 14 classroom renovation was ready when school started. The old administration building is demolished and the metal stud walls are in place.

Bradford Project:

Bradford is moving along. The exterior board is up and metal stud walls are in place in the interior. HVAC units are in place and roofing is complete. We are still anticipating a January completion on this building.

Reagan Project:

Upstairs was ready for occupancy in August. The demolition on the downstairs is well underway.

Lake View Project:

Plans are on the street for bids and we will open the bids on October 2nd.