Bond Progress Report - 12/6/2012

December 6, 2012

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Work continues on the last four classrooms in the main building. This area should be completed by the first of the January. We will try to move into the space during the Christmas break. The portables have been removed and dirt work on the track and field should begin next week.

Goliad Project:

This project is complete.

San Jacinto Project:

Punch list items, doors and hardware, and mechanical equipment enclosure are all in the final stages of completion. This job should wrap up by Christmas. We will complete the landscaping after the contractor is finished and off site.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations: The Student Service Center is complete and operational.

Banneker 1: - Complete.

Banneker 2: Complete.

Schweitzer: - Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Construction work is in the final stages at Holmes. Clean-up has started and will be complete this week. We will wax floors next week and be ready to move in starting December 26th.

Newton: Asbestos abatement will begin on Newton on January 7th. We will relocate classes during the Christmas break.

Crockett Project:

The south wing of the original school is almost complete. We are waiting on the millwork to be stained and installed. This wing should be ready for move-in during Christmas break. The middle wing is coming along and I anticipate it being ready around February 1.

Glenmore Project:

Work continues on the office building. It looks like it will be February before this is complete. The two classroom addition is progressing and should also be complete in early January.

Bradford Project:

Painting is in progress and should be complete soon. Flooring is in progress in the kitchen area. This building is scheduled to be complete around February 1st.

Reagan Project:

Reagan construction is coming along. The stud walls are almost complete and all electrical and plumbing rough-in is 95% complete. Drywall has started in a few areas. Completion of this area will not happen before February.

Lake View Project:

The construction site has been fenced and dirt work could start as early as next week. We should have all our permits from the city this week. Demolition has started in the ROTC building and walls are going up to divide the space.