Bond Progress Report - 1/21/2013

January 23, 2013

Click here to see photos of current Bond projects.

Lee Project:

Last 4 classrooms are complete. Moved in Jan. 2
Track drainage is complete
Punch list items are being worked
Track dirt work should begin Jan 14
95% complete

San Jacinto Project:

Punch list items underway
Touch-up paint being worked
New doors and hardware being installed
99% complete
Landscaping and some sidewalk work will come later

Central Project:

Holmes is complete and in operation
Moved-in during Christmas break
Newton vacated and abatement has started
Tennis court parking is complete
Punch list items will be worked in next month

Crockett Project:

New entrance is progressing
South wing complete and moved into Jan. 2
Middle wing is moving ahead
Hopefully will move late February
Structural issues have surfaced with old library wing

Glenmore Project:

Work continues on the administration
New windows should start Jan 14
Admin wing ready in March
Tile is down in 2 classroom addition
February is move-in date for these rooms

Bradford Project:

Painting is nearing completion
Data and electrical wiring in progress
Ceiling grid complete
Flooring is being laid
Curbs and side-walks are in around parking
Kitchen equipment is installed
Move near middle of February

Reagan Project:

Drywall complete downstairs
Tape and float started for painting
Wainscot tile will begin week of Jan 21
Structural steel due Jan 14
Late March move-in

Lake View Project:

Walls are up in ROTC for storage and new ISS
Paint and flooring will follow
ISS should be ready first of Feb.
New building pad is complete
Pier holes to begin Jan 14

Bond Completion Dates

Complete to date: Santa Rita, Holiman, Goliad

Complete 2012: Lee (building only)

Complete 2013: Crockett, Glenmore, Reagan, San Jacinto, Lake View, Lee track

Complete 2014: Central, Bradford