Bond Progress Report - 3/7/2013

March 8, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Few punch list items left for interior
Track is coming along and should be completed in May

Goliad Project:

This project is complete.

San Jacinto Project:

Few punch list items left to complete.
Final pay app and completion should occur no later than March 20.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Abatement is complete; Demolition complete; Elevator room under construction; Metal studs underway; Plumbing, electrical, data all underway

Crockett Project:

Portables being removed to start new drive and parking
Stucco going up in front of building
Office wing progressing and should be ready mid-April
Old library wing still moving slowly

Glenmore Project:

Moved back into the renovated administration wing last week.
4 and 6 classroom additions emptied and ready for abatement and construction
Approved a $350,000 change order to renovate 6 classroom wing

Bradford Project:

Moved into new addition two weeks ago
South wings, old office , old cafeteria areas being abated and prepped for renovation
Approve $1,000,000 to enclose all corridors on campus

Reagan Project:

First floor area is about 80% complete
Scheduled to move in mid-April
Wainscot tile going up, painting touch-up in progress, and ceiling grids going up
Waiting on flooring

Lake View Project:

Moving ahead quickly
Slab is down and steel is up
Roof decking will follow in the next two weeks as well as metal stud walls
ISS room is complete