Bond Progress Report - 4/2/2013

April 2, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Few punch list items left for interior
Track is coming along and should be completed in May

Goliad Project:

This project is complete.

San Jacinto Project:

Few punch list items left to complete.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Metal studs and drywall complete, Tape, float, and texture has started, Plumbing, electrical, data all underway

Crockett Project:

New drive and parking well underway
Flooring being installed in office wing
Office wing progressing and should be ready mid-April
Old library wing still moving slowly

Glenmore Project:

4 and 6 classroom additions have been abated and demolition is complete
Rough-in for plumbing and electrical well underway
Approved a $350,000 change order to renovate 6 classroom wing

Bradford Project:

Demolition of south end is almost complete
Exterior concrete being removed for corridor enclosures
Electrical, plumbing, data all starting rough-in

Reagan Project:

First floor area is about 80% complete
Scheduled to move in early May
Wainscot tile going up, painting touch-up in progress, and ceiling grids going up
Waiting on flooring

Lake View Project:

ISS room is complete
Roof deck is complete on new wing
Metal stud walls starting to go up
Wood decking will begin in the next few weeks