Bond Progress Report - 5/2/2013

May 3, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Few punch list items left for interior
Track is coming along and should be completed in May

Goliad Project:

This project is complete.

San Jacinto Project:

Few punch list items left to complete.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Paint and ceiling grid in progress, Lights have been installed in most rooms, Downstairs area has studs and windows in place, Should be ready to occupy in early June

Crockett Project:

Office wing is occupied
Old office demolition underway
Texture and painting underway in former library wing
Parking, sidewalks and drive on north side underway

Glenmore Project:

4 classroom addition has drywall installed and restroom tile has begun
Ceiling grid has started in 4 classroom wing
6 classroom addition has paint and ceiling grids complete
Wainscot being installed in 6 classroom wing

Bradford Project:

Stucco is almost complete in both south wings
Corridors are enclosed on the south
Former cafeteria is gutted and renovations have begun

Reagan Project:

First floor area is ready for occupancy on May 7th
North wing will be vacated and work will continue in that wing

Lake View Project:

Exterior stucco is going up quickly
Interior spray-on insulation is in progress
Drywall going up in classrooms
Electrical and data beginning