Bond Progress Report - 6/14/2013

June 14, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Few punch list items left for interior
Track is scheduled to be installed in the next few weeks

Goliad Project:

This project is complete.

San Jacinto Project:

Few punch list items left to complete.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Upstairs is complete except for some minor items, Downstairs area has drywall, paint, ductwork in place and lighting underway, Moved into upstairs rooms June 3rd, Completion should occur by end of June

Carlyle: Abatement is underway, Renovations should begin mid-July

Crockett Project:

Office wing is occupied
Old office ready for paint and flooring
Former library wing flooring is going down and ceiling grid is up
Painting is almost complete in all wings
Parking, sidewalks and drive on north side complete

Glenmore Project:

4 classroom addition restroom tile has begun
Ceiling and painting complete in 4 classroom wing
Millwork in place in 4 classroom wing
6 classroom addition complete except hallway flooring
Demo of west wing has started

Bradford Project:

Corridors are enclosed on the south wings
Floor tile in all classrooms in south wings
Wainscot being installed in south wings
Demo has begun in north wing
Abatement starts Monday on middle wings

Reagan Project:

Moved into office areas in late May
Demolition underway on north and cafeteria wings

Lake View Project:

Exterior stucco waiting for curing and paint
Interior walls in place and texture and paint 95% complete
Ceiling grid beginning