Bond Progress Report - 8/1/2013

August 8, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

Few punch list items left for interior
Track, and fencing are complete, sod at 98%

Goliad Project:

This project is complete.

San Jacinto Project:

Landscaping is almost complete.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Complete

Carlyle: Demolition is complete and renovation has begun, Metal studs up in most of the building, Elevator shaft ready for concrete, Completion date is November 1

Crockett Project:

Old office area complete
Exterior touch-up and clean-up underway
Interior is 99% complete and occupied
Landscape finishing up

Glenmore Project:

4 classroom addition restroom partitions underway. Rest of building is 99% complete
6 classroom addition complete
West parking lot is underway
Cafeteria restroom, kitchen and eating area renovation about 70%
East parking lot is 95%
Landscape and other areas are progressing
All buildings will be ready for school to start. Exterior work may still be in progress

Bradford Project:

Corridors are enclosed on all wings
South wings and old office are 95% complete
North wing is moving ahead quickly and will be ready for start of school
Old cafeteria and library should be ready by August 20th
Two interior wings will not be complete at start of school

Reagan Project:

North classrooms are about 90% complete
Cafeteria is well underway and will be ready for start of school
4 classrooms in east hallway are underway but will not be ready when school starts

Lake View Project:

Building is 95% complete
Final cleaning begins Aug 5
Move-in begins Aug 12
Exterior work in progress and should finish in next two weeks