Bond Progress Report - 9/4/2013

September 16, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

This project is complete.

Goliad Project:

This project is complete.

San Jacinto Project:

This project is complete.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Complete

Carlyle: Drywall almost complete upstairs, Elevator shaft pored and ready for masonry, Ductwork complete, Plumbing rough-in complete upstairs, Completion date is November 1, Handel abatement and demolition will follow Carlyle

Crockett Project:

This project is complete.

Glenmore Project:

All classroom areas are complete
Cafeteria and kitchen are complete
West parking is complete
Restroom addition to cafeteria is about 90% complete
Exterior fencing, landscaping and clean-up are underway
All areas should be complete in early October

Bradford Project:

Corridors are enclosed on all wings
South wings and old office are complete
Two north wings are complete
Work progressing on middle wing and north/south hallway
Library should be ready by the end of this month

Reagan Project:

North classrooms are complete
Cafeteria is complete
4 classrooms in east hallway are underway
Plumbing inspections due this week

Lake View Project:

Building is complete
Site work modifications underway
East side parking progressing