Bond Progress Report - 10/4/2013

October 4, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

This project is complete.

Goliad Project:

This project is complete.

San Jacinto Project:

This project is complete.

Central Project:

Kelton Ag and building maintenance shops: Complete

Tucker Admin/classroom wing: Complete.

Phase 3 Renovations:

Banneker 1: Complete.

Banneker 2: Complete.

Schweitzer: Complete.

Cafeteria: Complete

Courtyard: Complete

Michelangelo: Complete

Holmes: Complete

Newton: Complete

Carlyle: Drywall complete upstairs, Elevator shaft masonry is being erected, Plumbing rough-in complete, First coat painting complete, Tile wainscot in hallway started, Completion date is November 15, Handel abatement and demolition will follow Carlyle

Crockett Project:

This project is complete.

Glenmore Project:

All classroom areas are complete
Cafeteria and kitchen are complete
West parking is complete
Restroom addition to cafeteria is complete
Exterior fencing, landscaping and clean-up are underway
All areas should be complete in early October

Bradford Project:

Library is complete. Books moved in this week.
“D” wing millwork is in and stained
First coat of paint applied
Boards are installed
Flooring to start this week

Reagan Project:

4 classrooms in east hallway are underway
Plumbing & electrical rough-in inspections are complete
Stud walls are complete

Lake View Project:

Building is complete
Site work modifications underway
East side parking progressing