Bond Progress Report - 11/4/2013
November 4, 2013
Santa Rita Project:
This project is complete.
Holiman Project:
This project is complete.
Lee Project:
This project is complete.
Goliad Project:
This project is complete.
San Jacinto Project:
This project is complete.
Central Project:
Kelton Ag and building maintenance shops: Complete
Tucker Admin/classroom wing: Complete.
Phase 3 Renovations:
Banneker 1: Complete.
Banneker 2: Complete.
Schweitzer: Complete.
Cafeteria: Complete
Courtyard: Complete
Michelangelo: Complete
Holmes: Complete
Newton: Complete
Carlyle: Painting on top level almost complete, Ceilings being padded out, VCT tile will begin this week, Lower level painting will begin this week, Elevator equipment install will begin this week, Completion scheduled around Thanksgiving, Handel abatement and demolition scheduled to begin December 2, 2013
Crockett Project:
This project is complete.
Glenmore Project:
All classroom areas are complete
Outside work still progressing with concrete and clean-up
Playground is installed and waiting on fall material
Bradford Project:
Library is complete. Books moved in this week.
“D” wing is complete
North/south corridor is moving along quickly
Painting and tile work well underway
Should finish this area by mid-November
Portables will be moved by December 1 and parking area can begin on west side
Reagan Project:
4 classrooms in east hallway are ready for paint and wainscot
Classrooms ready for paint
Restrooms ready for tile
Completion around December 1
Lake View Project:
Building is complete
Site work modifications underway
Additional sidewalks being added due to increased foot traffic
East side parking complete