Bond Progress Report - 12/5/2013

December 9, 2013

Santa Rita Project:

This project is complete.

Holiman Project:

This project is complete.

Lee Project:

This project is complete.

Goliad Project:

This project is complete.

San Jacinto Project:

This project is complete.

Central Project:

Central construction is complete in all buildings.
Classes began in Carlyle after Thanksgiving.
We are currently working on abatement at Handel with demolition to begin during the Christmas break with final completion near the end of February. This will complete all work on this project.

Crockett Project:

This project is complete.

Glenmore Project:

Outside work still progressing with concrete and clean-up
Playground is installed and waiting on fall material

Bradford Project:

All buildings are in use and complete except for punch list items.
New library shelving will be installed Dec. 10th.
Outside concrete work continues
Parking lot on west side will begin after portables are removed

Reagan Project:

4 classrooms in east hallway are moving very slowly due to availability of tile layers
Rooms should be ready for occupancy during Christmas break

Lake View Project:

Doors on east end should arrive any day now
Install will occur during Christmas break
Landscaping improvements will also begin soon