Bond Progress Report - 1/14/2014

January 14, 2014

Completed Projects:

Santa Rita Elementary
Holiman Elementary
Lee Middle School
Goliad Elementary
San Jacinto Elementary
Crockett Elementary

Central High School Project:

Central construction is complete in all buildings.
Demolition of Handel is complete
Work began this week on finishing emergency access to gyms, landscaping and drainage

Glenmore Elementary Project:

Outside work is complete except for some minor finish work
Playground is installed and in use
Final asphalt and concrete work is complete

Bradford Elementary Project:

All buildings are in use and complete except for punch list items.
Parking lot on west side and all fencing will begin after portables are removed

Reagan Elementary Project:

4 classrooms in east hallway are ready and we will move in on Monday, 1/20/14
Restroom tile being reworked in cafeteria hallway
Pricing being finalized for early childhood wing on the south side of campus

Lake View High School Project:

Doors on east end are installed
Entry landscape area complete
Landscaping improvements will also begin soon