School Bond 2008 - Lee Middle School

Campus: Lee Middle School
Architect: Huckabee Inc.
Estimated Cost: $14,150,750
View a detailed PDF of this plan
ADA Compliance
- Ramps/Doors/restrooms
Renovations and Repair
- Fully renovate boys’ gym, field house, girls’ gym, cafeteria, band hall, and main building
- Convert existing library to special use/computer lab
- Need storage space
New Additions
- Provide new library (4,500 sq ft), 16 regular classrooms, 2 special use spaces (approx 17,000 sq ft) to replace
portables - New field house and weight room (approx 7,000 sq ft)
Site Improvements
- 3 or 4 lane running track/pole vault/high jump/long jump runways
Mechanical/Electrical/Plumbing
- Replace HVAC, add Energy Management System, upgrade plumbing, upgrade electrical, replace interior lights,
add additional exterior lighting, upgrade fire alarm system
Other
- Removal of portables