Bond Construction Update – June 15, 2026

Brooks Wehner of KFW Architects shared updates on Lake View High School’s new concession facility and the Fannin Elementary project during the June 15, 2026 Regular Board Meeting.

Lake View High School Concession Facility

  • Construction documents for the Lake View concession facility were issued on March 20.
  • Bids were received on April 15, and the contract was awarded on April 19.
  • The project is currently awaiting final permit review from the City of San Angelo.
  • Lee Lewis Construction has been in contact with the city permitting department, and the review process is nearing completion.
  • KFW is reviewing product submittals, primarily related to mechanical, electrical and plumbing components, so materials can be ordered and the project can continue moving forward.
  • Mobilization is expected soon, with construction fencing and a job trailer anticipated in the near future.
  • The facility will include a ticket booth for ticket sales and point-of-sale operations.
  • The concession area will include refrigerators, sinks, a warming cabinet and food preparation space.
  • A connected storage area will include a freezer, cooler, ice maker and shelving for dry goods.
  • The facility will include men’s and women’s group restrooms located near the football, baseball and softball fields.
  • Officials’ changing rooms will be located on the south side of the building, facing the main campus, for referees and umpires to use before games.

Fannin Elementary

  • Construction documents for the Fannin Elementary project were issued on May 29.
  • KFW is currently answering pre-bid RFIs submitted through the construction manager from interested subcontractors and trade partners.
  • A pre-bid walkthrough was held last week, allowing interested trade partners to walk through the campus.
  • Lee Lewis Construction is currently soliciting bids from trade partners.
  • Bids are expected to be finalized soon, with a Guaranteed Maximum Price anticipated for board consideration shortly after.
  • The permit application is expected to be submitted this week.
  • Once the GMP is delivered and approved, construction mobilization is expected to begin, with dirt work anticipated in early July.