The foreground displays %222025 Bond Update%22 with a date and logos, while the background features the %22SAN ANGELO ISD%22 logo and slogan.
A timeline of San Angelo ISD's 2025 bond projects is presented against a white background, with the foreground detailing specific projects and their completion years from 2025 to 2029.
A timeline chart in the foreground displays San Angelo ISD's 2025 bond projects with their design, bidding, construction, and move-in phases across several years, while the background is a solid blue color with the San Angelo ISD logo at the top.
A project status update for Crockett Elementary Addition is presented with a 3D rendering of the building in the background.
Construction is underway on a brick building with a partially completed roof, while in the foreground, a dirt path is lined with wooden barriers.
A person in a lift works on a wall in the foreground, while a blue painted wall and construction materials are visible in the background.
A construction update for McGill Elementary Phase II Addition shows a rendering of the school with new areas highlighted in purple, set against a backdrop of existing buildings and a street.
Construction is underway on McGill Elementary Phase II Addition, with heavy machinery visible in the foreground and the new building under construction in the background.
A brick building with large windows and a circular logo is shown in the background, while the foreground displays text about New Glenn Middle School's construction status and recent activities.
A rendering of a modern school building with a street and cars in the foreground is presented alongside project details and recent activity updates.
A blueprint of a school addition and renovation project is displayed, with text detailing project status, architect, contractor, and recent and upcoming activities in the background.
A white background displays %22THANK YOU!%22 in blue text above the %22SAN ANGELO ISD%22 logo and tagline, with a %222025 Bond Update%22 and date in the lower portion, alongside smaller logos.
Bond Construction Update – June 8, 2026

RJ Lopez with Parkhill Architects provided an update on 2025 Bond construction progress during the June 8, 2026 Preagenda Board Meeting. Project timelines remain on schedule, with several projects continuing through design, bidding and early construction phases.

Crockett Elementary

  • Crockett Elementary continues to move quickly toward completion.
  • Crews are working on painting, finish work and interior touch-ups.
  • Windows for the cafeteria have arrived, allowing that portion of the project to continue moving forward.
  • Exterior work and brick work are progressing, and crews have started work on drives and approaches outside the building.
  • The project remains on track to be ready for students and teachers by August 1.

McGill Elementary

  • McGill Elementary is progressing smoothly.
  • Utility work is underway at the campus.
  • Crews are building up the pad for the new additions.
  • Work has started on concrete footings and preparation for the concrete foundations.

Glenn Middle School

  • The new Glenn Middle School project remains on schedule.
  • Parkhill is finalizing construction documents for the project.
  • The construction documents are expected to go to Lee Lewis for bidding in June.
  • A Guaranteed Maximum Price, or GMP, is expected to be presented in July.

Lake View High School

  • Lake View High School is also expected to come back to the Board in July for a GMP.
  • The project is continuing through the planning and preconstruction process.
  • Several major bond projects are expected to move into construction in August.

Central High School

  • Construction activity has begun at Central High School with the water line relocation project.
  • The existing water line is being rerouted so that an active city water line will no longer run beneath existing campus buildings.
  • The water line relocation route has been dug, pipe has been placed, and crews are working on covering the pipe.
  • The work began a little more than a week before the meeting and is already slightly ahead of schedule.
  • The early start helps keep the overall Central High School project moving on schedule.

Additional Updates

  • Project timelines continue to align with the original bond schedule.
  • The district’s bond project dashboard is helping provide timeline information and answer questions from the community.
  • Bond-related activity is also taking place across multiple athletic fields throughout the district.