A white background displays the %22SAN ANGELO ISD%22 logo and slogan in the upper portion, with %222025 Bond Update%22 and the date in the lower portion, alongside smaller logos.
A timeline of San Angelo ISD's 2025 bond projects is presented against a white background, with the foreground featuring a detailed project breakdown by year.
A timeline chart displays San Angelo ISD's 2025 bond projects with colored bars indicating design, bidding, construction, and move-in phases across five years, set against a blue background with a school district logo at the top.
A project status update for Crockett Elementary Addition is presented with a 3D rendering of the building in the background.
Two side-by-side photos show a brick building under construction in the foreground with a cloudy sky in the background.
In the foreground, unfinished walls and construction materials are visible, while the background reveals exposed mechanical ducts and overhead piping in a building under construction.
A construction update for McGill Elementary Phase II Addition shows a rendering of the school with new sections highlighted in purple and blue, surrounded by existing buildings and a street in the background.
Construction equipment sits on the dirt in front of the partially built McGill Elementary Phase II Addition, with a brick building visible in the background.
A modern school building with a playground in the background is surrounded by landscaping and a street in the foreground.
Construction is underway on McGill Elementary Phase II Addition, with a dirt lot in the foreground and the school building and surrounding trees in the background under a cloudy sky.
Cars are parked in the foreground of a modern brick and white building with trees and people walking around it under a cloudy sky.
A brick building with large windows and a school logo is shown in the background, while the foreground displays project information for New Glenn Middle School.
A modern brick school building with a courtyard in the foreground and a desert landscape in the background is presented in two renderings.
A rendering of a modern school building with a street and cars in the foreground is overlaid with text detailing the Lake View High School Addition and Renovation project.
A blueprint of Central High School's addition and renovation project displays a layout of the auditorium, gymnasium, kitchen/cafeteria, health science, and culinary lab in the foreground, with project details like status, architect, contractor, and completion date in the background.
A modern architectural rendering of a school addition with a prominent glass entrance in the foreground and a clear sky in the background.
A digital rendering of a modern school building with a beige and gray facade is presented against a plain gray background, with text at the top indicating %22Central High School Addition and Renovation%22 and %22Status: Design Development.%22
Architectural elevations of a modern building with a prominent logo are displayed against a white background, with a material legend in the top left corner.
A digital banner for San Angelo ISD's Bond 2025, featuring a large %22THANK YOU SAN ANGELO!%22 message in the foreground, is superimposed over a blurred image of a modern school hallway in the background.
A donut chart displaying bond budgets by project packages, with a legend on the right, is presented on a white background with a dark header.
A bar chart displays expenditure tracking with a list of packages on the right, showing spent to date and remaining budget percentages.
A white background displays %22THANK YOU!%22 and %22SAN ANGELO ISD BUILDING FUTURE-READY GRADUATES%22 in blue and yellow text, with the San Angelo ISD logo on the right, and a %222025 Bond Update%22 with a date and Parkhill logo at the bottom.
Bond Construction Update – May 11, 2026

During the May 11 preagenda board meeting, RJ Lopez with Parkhill Architects provided the Board of Trustees with an update on progress across San Angelo ISD’s 2025 Bond projects. 

Crockett Elementary School

  • Exterior brick work is nearing completion on the kitchen and classroom addition areas.
  • Crews continue enclosing the new cafeteria portion of the project.
  • Interior work is underway, including ductwork, mechanical systems, and installation of kitchen freezer and cooler equipment.
  • The project remains on track for an August 2026 opening.

McGill Elementary School

  • Site clearing and preparation work continues as crews prepare for new additions.
  • Updated renderings were shared showing the future library and administrative addition.
  • Additional renderings highlighted the planned classroom expansion areas.
  • Construction remains on schedule as the project moves into the next phase.

Glenn Middle School

  • Design teams continue refining construction documents ahead of bidding.
  • Updated exterior renderings were presented showing continued development of campus materials, landscaping, and sidewalks.
  • Architects are working to finalize details before the project moves into the bidding phase.

Lake View High School

  • The Lake View High School additions and renovations project is expected to go out for bid in the coming weeks.
  • Bids are anticipated over the summer, with construction expected to begin around August.

Central High School

  • Updated exterior renderings were shared for the additions and renovations project.
  • Designs included concepts for the new student entry, auditorium frontage, cafeteria connection, and gymnasium area.
  • Design teams continue refining exterior materials, colors, and site details.
  • The underground water line project remains scheduled to begin this summer.
  • Major construction could begin later this fall.

Bond Financial Dashboard

  • District leaders announced that the new Bond Financial Dashboard is now available through the SAISD 2025 Bond website.
  • The dashboard provides updates on project budgets, spending progress, and bond package information for the community.

Bond 2025 Updates