Main Menu

Explore More

District Menu

A group of people in blue shirts gather around a concessions building and ticket booth in the foreground, with a stadium track visible in the background.
People in blue and white school spirit wear walk towards a modern concessions and ticket booth building with a chain-link fence and sports field visible in the background.
Children play on a colorful playground in the foreground, with a brick school building and a cloudy sky in the background.
Children gather on a tiered outdoor seating area in front of a modern brick school building with a blue roof, set against a grassy lawn and trees.
Bond Construction Update – May 18, 2026

Brooks Wehner with KFW Architects provided an update on two Bond 2025 projects during the May 18 Regular Board Meeting: the Lake View High School concession building and Fannin Elementary School.

Lake View High School Concession Building

  • Lee Lewis Construction has been approved as the contractor for the Lake View High School concession building project.
  • The project plans have been submitted for permitting.
  • The contractor is beginning mobilization, with construction fencing expected to go up soon.
  • KFW Architects is working with the City of San Angelo through the permitting process and responding to any questions.
  • Construction progress is expected to begin shortly after mobilization.
  • Updated renderings were shared showing the concession building with additional visual details to help bring the project concept to life.

Fannin Elementary School

  • KFW Architects shared updated renderings of the planned 12-classroom addition and playground area at Fannin Elementary School.
  • The design includes a large covered overhang at the building exit, providing a transition area from the classroom addition toward the playground and existing sport court.
  • The project team is working to complete drawings and construction documents by May 29.
  • Once complete, the documents will be turned over to Lee Lewis Construction for pricing and permitting.
  • A guaranteed maximum price is expected shortly after the May 29 deadline.
  • Construction is expected to begin during the summer, with site work anticipated shortly after July 4.
  • The project is expected to take approximately 12 to 12 and a half months, with the goal of having the addition ready by August 2027.
  • The design takes into account the elevation changes on the Fannin Elementary site, including monumental stairs, limestone block seating areas, ramps and other accessible pathways.
  • KFW Architects and Lee Lewis Construction have been meeting regularly to coordinate construction planning and campus logistics for the project.

Bond 2025 Updates