A project status update for the Crockett Elementary Addition features text details and a 3D architectural rendering of a building against a plain white background.
A tan brick cafeteria building with a black metal railing ramp sits in the foreground under a bright blue sky with scattered clouds.
A modern cafeteria with long white tables and blue seating sits before a dark stage, paired with a view of a brightly lit, minimalist hallway.
A classroom with student desks and storage bins sits before a window, paired with an outdoor playground featuring a blue shade canopy over green turf.
A presentation slide about the McGill Elementary Phase II Addition features project details and a list of recent activities in the foreground, with an aerial photograph of the construction site in the background.
Construction equipment and a white pickup truck sit in the foreground of a building under construction with blue weather-shielding, set against a clear blue sky.
A steel building frame stands under a clear blue sky in the foreground, with a distant building and trees in the background.
A project update slide for the New Glenn Middle School features construction details and a list of recent activities on the left, with a digital rendering of the school's brick exterior and landscaping on the right.
Students walk through a modern, multi-level school atrium with a skylight ceiling and a dark blue accent wall.
Students study and socialize in a modern school library featuring green accents and large windows in the background.
Spectators sit in chairs and bleachers surrounding a polished wooden basketball court inside a modern gymnasium with %22RAIDERS%22 written on the far wall.
A modern gym foreground features rows of weight benches and barbells set against a background of a green ceiling and a wall with %22San Angelo Texas%22 branding.
A presentation slide detailing the Lake View High School Addition and Renovation project features a digital architectural rendering of a modern school building under a blue sky in the foreground and project specifications in the background.
Manicured shrubs and a concrete walkway lead toward a modern school building with blue support columns under a cloudy blue sky.
A man stands by a podium while soldiers hold flags in the foreground, with a large green tree and a white tent in the background.
A group of people in hard hats use shovels to break ground in the foreground, with the Lake View High School Auditorium building standing in the background.
A group of musicians in traditional grey and blue embroidered outfits play violins and guitars in the foreground against a blurred outdoor background of trees and a building.
Two side-by-side photos show construction workers operating machinery and cleaning a site in front of Lake View High School buildings.
Text detailing the status and timeline of the Central High School Addition and Renovation project sits above a series of architectural floor plans for an auditorium, gymnasium, kitchen/cafeteria, health science area, and culinary lab.
Two side-by-side photos show a school construction site with orange cones and equipment in the foreground and school buildings and large trees in the background.
A modern school building with a large parking lot and cars in the foreground sits under a bright, cloudy blue sky.
A modern school building with a parking lot and cars in the foreground sits under a bright blue sky with fluffy white clouds in the background.
A crowd of students fills a modern auditorium with tiered seating in the foreground, facing a large blue curtained stage set against a high ceiling with acoustic panels in the background.
Students gather on a tiered seating area and walk through a modern, high-ceilinged school lobby featuring blue architectural ceiling baffles.
Students walk through a modern school lobby featuring a ticket booth in the foreground and a multi-level interior with a sculptural ceiling installation in the background.
Bond Construction Update – September 21, 2026

Hector Santiago of Parkhill provided an update on Bond 2025 construction projects during the San Angelo ISD Board of Trustees meeting on Sept. 21, 2026. He reported that the overall construction timeline remains on track.

Crockett Elementary School

  • The new cafeteria and kitchen have received a certificate of occupancy. The classroom addition received its certificate before the school year began.
  • Crews are addressing remaining punch list items and preparing documentation to close out the project.

McGill Elementary School

  • Structural steel and metal decking are complete in both construction areas.
  • Metal stud framing was nearing completion in Area A. Framing and electrical work are next in Area B, where some mechanical work has begun.
  • The overall project is scheduled for completion in June 2027. Santiago said he expects Area A to be completed around January or February 2027 and will follow up with the contractor on that timeline.

New Glenn Middle School

  • The plans remain under City review. The design team has responded to the first round of comments, and a site permit has been issued.
  • The site permit allows some work to begin while the remaining building permits are processed. A notice to proceed with construction has not yet been issued.
  • Students are using the practice fields near the stadium while the field west of Glenn is within the construction area.

Lake View High School

  • The portable buildings and overall project site plan have received permit approval, allowing work on site to begin.
  • Plumbing and electrical inspections have been requested for the portables.
  • Site clearing and demolition of concrete sidewalks have begun near the planned Mariachi building.

Central High School

  • The construction manager received bids, and a guaranteed maximum price was presented for the board’s consideration at the meeting. Project plans have been submitted for review.
  • Preparatory work, including water line work, was completed over the summer while students were away from campus.
  • The planned gymnasium will have a capacity of 2,200.